DEP Cambria

时间:2007-04-27 16:27:57 作者:佚名 来源:筑能网

 

能源世界-DEP Cambria

地址: Ebensburg, PA 

建筑面积: 3,340 sq. meters

竣工日期: October 2000 

高度: 2-story building 

能源利用: Ground-source heat pumps are linked to a closed-loop, ground-source heat pump well field that provides HVAC heating and cooling supply as well as domestic hot water heating. Raised-access flooring provides an underfloor supply air plenum for displacement heating and cooling air distribution through floor-mounted air diffusers.

A 14.3 kW PV array mounted on south-facing sloped roofs provides 28% of the total energy costs. Several of these PV panels are mounted on solar tracking devices.

Heat recovery air-handling units provide ventilation make-up air separated from conditioned air, thereby allowing for conditioned air equipment to be shut off when not needed. Ventilation air is preconditioned through energy recovery, which also provides the necessary dehumidification for the system.

Fourth-generation design of light shelves on south-facing windows increases lighting levels by reflecting natural light deeper into interior spaces; at the same time, cooling loads are reduced by shading windows from exposure to summer solar radiation.

Site-specific reverse-baffle solar shading devices were designed to shade other south-facing windows from high-altitude summer sun while allowing low-altitude winter solar radiation to penetrate into interior spaces. Second floor south-facing windows are shaded via integral roof overhangs.

Lighting power density is reduced to an average of less than 0.75 W/ft2 (8 W/m2), which significantly reduces both electrical energy consumption and cooling loads. This was accomplished by integrating the following components: split task/ambient lighting scheme; indirect fluorescent lighting fixtures with T-8 lamps and electronic dimming ballasts controlled by light-level sensors; natural daylighting via clerestory window monitors; occupancy-sensored switching at workstations, toilet rooms, and conference rooms; roll-down solar shades and south-facing windows; compact fluorescent lighting fixtures with vertical lamp configurations; and LED exit signs.

Manufactured wiring distribution systems incorporate relocatable floor boxes mounted in access floor panels with quick-disconnect cabling to provide maximum flexibility for tele-data and power provisions. Such flexibility supports workstation reconfigurations and minimizes chum rate costs.

The building's thermal envelope achieves high-performance levels by integrating exterior walls constructed of highly insulating—R-30 (RSI-5.3)—EPS structural concrete wall forms; high-density fiberboard roof decking laminated with an interior reflective surface coupled with 4 in. (100 mm) of rigid polyisocyanurate insulation to provide a composite roof insulation of R-33 (RSI 5.8); pre-manufactured aluminum-clad windows which provide triple-glazed, low-e coated, argon-filled insulating glass with a whole-unit U-value of 0.29 (1.6 W/m2*C); storefront window fabrication including high-performance, thermally broken frames and triple-glazed, low-e coated, argon-filled insulating glass with a whole-unit U-value of 0.26 (1.5 W/m2*C); and a concrete floor slab on grade which is insulated with 2 in. (50 mm) of EPS rigid insulation.

This high-performance thermal envelope, in conjunction with space planning that locates no workstations directly adjacent to window walls, eliminated the need to design separate perimeter thermal zones and supplemental perimeter heating systems.

节水方案: Cambria's site selection, building placement, and parking layouts were integrated with existing site conditions in order to eliminate negative impacts on existing wetlands and to minimize the removal of existing trees.

The parking areas utilize grass planting pervious parking surfacing in order to minimize stormwater runoff. Impervious paving is limited to circulation aisles.

The exterior lighting design reduces light pollution. Required clearing of existing vegetation was limited to a maximum of 25 ft (7.6 m) from the building perimeter. The building is oriented along an east-west axis in order to maximize south and north solar exposures. High-albedo roofing materials and strategic planting of deciduous trees help reduce "heat island" effects. A significant portion of the site was left undisturbed. Indigenous plantings and other landscaping efforts resulted in no net increase in the rate of stormwater leaving the site.

Cambria's specified plumbing fixtures reduce aggregate water consumption to a level of water usage that equates to more than 30% less than the requirements of the federal Energy Policy Act of 1992.

The lavatories are equipped with extremely economical "push rod" automatic faucet controls that reduce water consumption by over 40% and minimize piping redundancies by mixing hot and cold water into single pipe supply lines.

The toilet rooms are equipped with waterless urinals that require no water supply or flush valves and minimize maintenance costs.

材料选择: Selection of building materials was based on the renewability of the resource, environmental effects associated with production of the product, and each product's recycled content and recyclability. Materials selection criteria resulted in specifying over 30% of building materials manufactured within 300 miles (480 km) of the project site.

Building plans include a centralized storage area for materials separation and recycling.

Diversion of Construction & Demolition Waste

The design of building and materials systems utilized modular dimensioning in order to minimize construction waste.

A construction waste management plan monitored recycling of cardboard, metals, concrete, wood, masonry, plastic, glass, gypsum board, insulation, beverage containers, carpet, and other materials during construction.

室内环境品质: Smoking is prohibited throughout the building.

All paints, adhesives, sealants, and coatings were selected to minimize VOCs and eliminate solvent-based products.

Floor-mounted air-distribution diffusers provide 100% ventilation efficiency. These diffusers also provide individually controlled thermal comfort: each occupant has the ability to control and vary the quantity of air delivered to his or her workspace. Operable windows are used throughout.

Building entrances are equipped with permanent floor mat systems which provide walk-off areas to help prevent particles from contaminating interior spaces.

Specifications include an IAQ management plan for construction that mandates protection and/or cleaning of ventilation systems and insures reduced levels of construction contaminants in the building prior to occupancy. The building is equipped with permanently installed indoor air quality monitoring devices for measuring humidity, temperature, CO2 levels, and VOCs.

新闻订阅】 【打印】 【网站论坛】 【字体: 】 【发表评论】 【关闭
现有 人对本文发表评论 [查看所有评论]
昵称:  请输入验证码:   看不清图片,请点击图片!
申请加精
相关文章

最新资讯
·可再生能源:如何从花瓶能源到主导能源
·陕西:清洁能源发展潜力大
·国际节能减排面面观
·新颁布条例如何推进民用建筑节能的开展?
·既有民用建筑节能改造艰巨 居民恐负担部分费用
·别让伪劣材料毁了建筑节能大业
·国家利益与能源战略
·从奥运看绿色节能材料走进生活
·后能源时代已经悄然来临
·从化石能源向新能源过度 三大细分行业前景各异
 
下载排行
·《ANSYS工程结构实例分析》
·《工程勘察设计收费标准(2002年修订本)》
·《室内设计基础》
·《大学生建筑设计优秀作品集》
·《建筑设计作品博览 国外建筑竞赛优秀作品精粹
·《节能技术实用全书》(上卷)
·《光与建筑》
·《家居装修精选方案》
·《钢结构设计原理》
·《建筑力学与建筑结构》
 
行业新闻
热点专题

风能时代离我们还有多远

绿色建筑评价标识

太阳能光伏

奥运场馆践行绿色奥运
政策分析
行业人物
郑时龄
孟宪淦:破解太阳能与建筑两张皮
最新论文
最新书籍

活性炭生产工艺原理与设计

《流体力学》
最新图纸
最新资料
招标信息
论坛精华

住房和城乡建设部科技与发展促进中心(CSTCMOC) 中国绿色建筑委员会(CHINAGBC) 国际智能、绿色建筑与建筑节能大会(IGEBC) 指定合作网站
承办:沃德高科(北京)科技有限公司
Copyright ©2007-2008 CHINAGB.NET.All Rights Reserved.   京ICP备07024683号
通信地址:住房和城乡建设部北附楼312室(100835)
联系信箱:nengyuanshijie163.com  传真电话:010-88585380
合作热线:010-88585610/11/12转814/813/810/  合作部:QQ:122236888 编辑部:769172617 

关于我们 - 联系我们 - 广告服务 - 友情链接 - 网站导航